The close attention of the leadership and a surprise reward worth VND 100 million are a great morale boost, recognizing the round-the-clock efforts of the officers, engineers and workers at the KNQ 1.3 Bonded Warehouse project.

Recently, during a business trip and on-site inspection at the KNQ 1.3 Bonded Warehouse project located at Huu Nghi International Border Gate (Lang Son province), Mr. Đinh Hùng Cường – CEO of CNCTech Global JSC met, visited and encouraged all personnel working at the site.
To commend their responsible work ethic, determination to overcome difficulties and the positive construction results achieved, Mr. Đinh Hùng Cường, on behalf of the company's leadership, decided to give a surprise reward worth VND 100 million to the Project Management Board (PMB) and the engineers and workers.

Conquering a series of important progress milestones
The "spot bonus" decision made right at the site is a deserved and timely recognition of the construction team's tireless efforts. Despite challenges in weather and construction conditions, the KNQ 1.3 project has excellently completed a series of landmark milestones, including:
- 100% of the steel structure completed: Ensuring maximum solidity and safety for the entire frame of the building.
- Roof construction completed: Providing safe cover and making it easier to speed up interior work regardless of weather conditions.
- First fiber-reinforced concrete pour successfully carried out: Marking an important step in applying modern construction techniques, meeting demanding standards for load capacity and durability of the bonded warehouse floor.

Affirming capability, moving toward a successful finish
Completing key items in succession within a short time not only affirms the professional expertise and professional project organization and management of the PMB team, but also demonstrates CNCTech Global's strong commitment: the determination to bring the KNQ 1.3 project to completion on schedule while strictly complying with technical quality and site occupational safety standards.


The VND 100 million reward from the CEO carries not only material significance but also timely moral encouragement, reflecting a corporate culture that always values and recognizes the contributions of employees at CNCTech Global.
With the strong construction momentum being maintained at the site, the officers, engineers and workers at KNQ 1.3 promise to keep up their form and conquer the next milestones to bring the project into operation soon, helping elevate logistics infrastructure capability in the Huu Nghi International Border Gate area.